Lake Delhi Dam Construction Progress Update – June 10, 2014

Delhi Dam Construction Progress Report #2

June 10, 2014

General Project Information

As discussed last time, the plan to rebuild Lake Delhi dam and restore the lake to its former lake level will be accomplished in two parts which have been called Phase 1 and Phase 2.

First, Phase 1 will restore the concrete portion of the dam on the north side of the river. Finally, Phase 2 work will follow later this summer will restore the earthen dike on the south side of the river including a new large concrete labyrinth overflow spillway.

Phase 1 was awarded to Lunda Construction Company, a large and experienced heavy structural midwest firm from Wisconsin in April 2014.

The important critical goal of Phase 1 work is to complete enough refurbishing work on the concrete structure to allow river water flow to be diverted through it from the current river bed flowing through the breeched dike area.

Current Project Progress and Status in last 10 days, June 1 to June 10, 2014

The important DNR permit allowing the entire project to be constructed including Phase 2 has been received late last week. This is great news for the project.

Phase 2 work is now ready to be bid and awarded which will lead to the completion of the dam rebuild project. The timing of the Phase 2 bidding will depend on being confident that Phase 1 work will be substantially complete by October allowing for the river to be diverted through the refurbished concrete structure. Right now in looks like Phase 2 work will be bid in July 2014 for an August 2014 contract mobilization to begin this work.

Project completion date is heavily dependent several factors including river flows being average or below, no weather extremes in the next 12 months, selecting a quality contractor for Phase 2 equivalent to our Phase 1 contractor and the actual flow in the river at the time needed to refill the lake.

Right now for planning purposes, we are planning for a July 4, 2015, date to resume enjoyment of Lake Delhi. it could be sooner if everything listed above goes great.

Specific Progress by Lunda on Phase 1 work through June 10, 2014 includes:

Work Progress from June 1, 2014, to June 10, 2014

Lunda finished installing scaffold in all spillways so subcontractor, EICS, from Farley, Iowa, can sawcut  Pier Noses for removal.

 

Continue removing silt and dewatering upstream and downstream. Approximately 90% of silt has been removed from downstream Stilling Basin.

 

Removed and disposed of all spillway concrete beams.

 

Excavation for upstream Rock Anchor Block is about 70% complete

 

Lunda has begun cleaning and roughening face of dam and drilling holes for Rock Anchor Block rebar anchorage.

 

 

Previous Work completed by Lunda

 

  • Lunda mobilized at the end of April and began by removing large rock and debris and building a cofferdam on the upstream side. Later a downstream cofferdam was build and material which filled the downstream side of the powerhouse was removed.

 

  • Demolition of all of the old spillway gates and related equipment was completed.

 

  •  installing scaffold in north and center concrete spillways.

 

  • Continue removing silt and dewatering in cofferdam areas.

 

  • Removed center spillway beam. Finished removing all gates and gate hoisting equipment.

 

  • Excavation for upstream Rock Anchor Block is 75% complete.

 

  • Lunda will begin constructing Rock Anchor Block then finish removing spillway beams and pier nosing.

Next Dam Construction Report – Tuesday, June 20, 2014

Pat Colgan

Lake Delhi Receives IDNR Permit

The Lake Delhi Combined Recreational Facility and Water Quality District’s application for a flood plain permit to reconstruct and maintain the dam was approved on 6/5/14 by the Iowa Department of Natural Resources.  This is the permit required for Phase II.
 
The District will share additional requirements along with the operating plan details in the next Lake Delhi Voice.
 

Dam Construction Progress Report – June 1, 2014

Delhi Dam Construction Progress Report

June 1, 2014

General Project Information

The plan to rebuild Lake Delhi dam and restore the lake to its former lake level will be accomplished in two parts which have called Phase 1 and Phase 2. First, Phase 1 will restore the concrete portion of the dam on the north side of the river. Secondly, Phase 2 will follow later this summer will restore the earthen dike on the south side of the river including a large concrete labyrinth overflow spillway.

Phase 1 was awarded to Lunda Construction Company, a large and experienced heavy structural midwest firm from Wisconsin in April 2014. Major components of their work is to inspect and refurbish the entire concrete structure which was constructed in 1926-1928, install new large steel gates to replace the original gates with all associated mechanical and electrical equipment, provide upstream and downstream cofferdams to allow the contractor to gain assess to the dam all the way down to bedrock, and other associated control and safety related equipment.

The important critical goal of Phase 1 work is to complete enough refurbishing work on the concrete structure to allow river water flow to be diverted through it from the current river bed flowing through the breeched dike area. This will then allow the Phase 2 contractor to complete a major cofferdam  across the current river bed which in turn will dry up the area. He will then begin the preparatory work to construct the earthen dike and labyrinth spillway on the south side.

Phase 2 work will be bid and awarded once the final DNR permit is received which we believe is eminent.

Specific Progress by Lunda on Phase 1 work through May 31, 2014 includes.

  • Lunda mobilized at the end of April and began by removing large rock and debris and building a cofferdam on the upstream side. Later a downstream cofferdam was build and material which filled the downstream side of the powerhouse was removed.

 

  • Demolition of all of the old spillway gates and related equipment was completed.

 

  • Begin installing scaffold in north and center concrete spillways.

 

  • Continue removing silt and dewatering in cofferdam areas.

 

  • Removed center spillway beam. Finished removing all gates and gate hoisting equipment.

 

  • Excavation for upstream Rock Anchor Block is 75% complete.

 

  • Lunda will begin constructing Rock Anchor Block then finish removing spillway beams and pier nosing.

 

Next Dam Construction Report – Tuesday, June 10, 2014

 

Pat Colgan

Minutes for Trustee Special Meeting – June 5, 2014

The Combined Lake Delhi Recreational Facility and Water Quality District

Board of Trustees Work Session

Thursday, June 5, 2014 – 6:30 p.m.

Maquoketa Valley Middle School Conference Room

Delhi, IA

The meeting of the Combined Lake Delhi Recreational Facility and Water Quality District Board of Trustees was called to order by President Steve Leonard at 6:35 p.m. at the Maquoketa Valley Middle School Conference Room.

Trustees present:  Leonard, Davidson, Schneider, Gifford, Kramer and Burger

Trustees absent:  Kray

Visitors: Ed Schmidt, Don & Pat Dede, John & Pauletta Carbaugh, Jason Wenger, Lou & Sue Christensen, Jody Antrim, Ken & Barb DeKlotz, Pat & Chloe Colgan, Wanda Davidson, Margie Schneider, Marcheta Cooey Lux

Leonard reviewed the agenda. Motion made by Burger, second by Gifford to approve agenda.  Motion carried.

Jason Wenger, from The Burrington Group, gave a short presentation on the septic bid package his firm was proposing for the Rocky Nook area.  A motion was made by Kramer, second by Gifford to approve the bid package.   There was much discussion regarding the inclusion of the Advantex system in the proposal.  Several Trustees expressed concern that having this specific system in the bid package would prohibit other systems from being looked at.  Wenger told the Trustees that he was trying to provide a package that the DNR would accept.  It was suggested that several Trustees meet with Dennis Lyons from the Delaware County Sanitation Department and Dan Olson from the Iowa Department of Natural Resources to come up with a solution to the language needed to put the septic system out for bid.  There are some time constraints as the agreement with the Rocky Nook calls for the system to be completed in November of this year.  Kramer amended her motion to table acting on the bid package, Davidson seconded.  Motion carried.

Kramer presented the Trustees with Lunda Construction’s second payment of $180,844.66.  Motion was made by Burger, second by Schneider to approve payment.  Motion carried.

Kramer asked the Trustees to approve filing submission of claims to the DNR for reimbursement per our agreement with the State of Iowa.  The total amount for reimbursement is $463,254.40.  This includes the two payments to Lunda Construction and two payments to Stanley Engineering.  Motion by Schneider, second by Burger to approve. Motion carried.

Leonard asked Kramer to provide an update on the Peck property demolition. Kramer told the board that demolition had begun and Randy Harbach felt he could complete the project in the next couple of days. Kramer also mentioned that everything regarding the demolition project had been cleared with the DNR.

Leonard announced to the board that as of this afternoon he had heard from Jon Garton with the IDNR regarding our Phase II permit.  Mr. Garton sent Leonard a letter stating that approval had been given for the flood plain permit to reconstruct and maintain the dam.   Leonard expressed that this was very good news for Lake Delhi.

 

There being no public comment, a motion was made by Burger, second by Gifford to adjourn.

Agenda for Trustee Special Meeting – June 5, 2014

The Combined Lake Delhi Recreational Facility and Water Quality District

Thursday, June 5, 2014

6:30 p.m.

Delhi Middle School Conference Room

Delhi, IA

 

  1. Call to Order
  2. Approve Agenda
  3. Consideration and possible action on Rocky Nook Septic System bid package
  4. Set date for opening of Rocky Nook Septic System bids
  5. Consideration and possible action on payment #2 to Lunda Construction
  6. Consideration and possible action approving submission of claims to the Iowa Department of Natural Resources for reimbursement.
  7. Public Comment
  8. Adjourn

 

 

 

 

Minutes for Trustee Regular Meeting – May 21, 2014

The Combined Lake Delhi Recreational Facility and Water Quality District

Board of Trustees Meeting

Wednesday, May 21, 2014 – 6:30 p.m.

Heritage Bank Conference Room

Delhi, IA

The meeting of the Combined Lake Delhi Recreational Facility and Water Quality District Board of Trustees was called to order by President Steve Leonard at 6:32 PM at the Heritage Bank Conference Room.

Trustees present: Leonard,  Kramer, Davidson, Schneider, Burger, Gifford, Kray

Trustees absent:  n/a

Visitors: Jim Locke, Ed Schmidt, Don Dede, Pat Dede, Larry Peter, Dave Larson, Jody Antrim, Dick Beck, Ben Pasker, Corey Groth, Dwayne Donels, Jim Willey, Dan Staebell, Dan Kimball, Gary Grant, Jason Wenger, Shirley Helmrichs, Carla Becker, John Hess, Sara Millhouse (Dyersville Commercial) and Pat Colgan by Skype 

Agenda was reviewed by Leonard and he asked for a change in the Lobbyist contract action to discussion.  Motion by Gifford to approve agenda with change, Burger second, all ayes, motion passed.

Leonard opened the public hearing for the Rocky Nook Area On-Site Wastewater Treatment and Water Main Improvements.  He explained to build the spillway required a purchase of property from the Rocky Nook Association (RNA).  In the purchase document between the District and RNA, there was an agreement by the District to replace the septic system as we would need to remove it for construction purposes. Wenger explained the design for the Rocky Nook system.  After discussions with Dennis Lyons (County Sanitarian) and Dan Olson of the DNR, the plan is to utilize 3 separate Advantex systems.  The design required the ability to service 34 locations.   The individual hook up is the responsibility of each property owner.  Wenger also noted that installation of new water services to each of the RNA properties was also required. 

 

Leonard opened up the public hearing to the community.  Larry Peter asked if there had been any discussion regarding the old house and office system – would it be a possibility to tie into this project while the contractors are there.  Wenger said it could work as the septic system for the house is not up to code so if we are thinking of using it again, the septic tank would have to be replaced.  However, it would need to have its own separate contained system.   Ed Schmidt asked who is responsible for the RNA system after it is installed and Leonard advised RNA has responsibility for ongoing maintenance.  Ben Pasker asked what the engineering cost estimate is? Wenger said $236,000 for both the septic and water system.  Jody Antrim asked if the Advantex system is the only one they looked at because he said a Weco (sp) system is half the price.  Wenger said looked at others and this is the recommendation based on their design and conversations with County Sanitation.  Wenger indicated if a contractor wants to propose a different system, he would analyze it.  Gifford said he would like the bid to advise that a contractor can propose a different system and it would be considered.  Wenger said he can add an addendum to explain that.  Since no further comments, a motion was made by Burger to close the public hearing, Davidson second.  All ayes, motion passed and public hearing was closed at 6:54 pm. 

Kray requested approval of 4/17/14 and 5/1/14 minutes.  Gifford made motion to approve, Kramer second.  All ayes, motion passed.

Kramer detailed billings for the General Fund.  Alliant Energy – $21.96; Hunt & Associates (Annual Compilation report) – $750.00; L&L Consulting – $2000; News Publishing – $26.24; Simmons Perrine Moyer Bergman – $520.05.  Billings for the Bond Fund are Lunda Construction for General – $119,872; for Demolition – $834.00; for Construction – $151,466.15 and Simmons Perrine Moyer Bergman – $3,268.75.  Kray made motion to pay billings for the General and Bond funds, Burger second, all ayes, motion passed.

Kramer gave review of the Financial report for month ending April 30, 2014. The General Fund began with a balance of $148,635.67 and after revenues and expenses, ended with a balance of $155,193.51.  The Debt Service Fund began with a balance of $327,215.43 and after revenues ended with a balance of $355,013.70.  The Dam/Spillway fund started with a balance of $5,346,302.06 and after revenues and expenses, ended with a balance of $5,244,522.43.  Motion to file financial reports by Davidson, second by Gifford, all ayes, motion passed.

Kramer covered compilation report received by Hunt & Associates through the County Auditor’s office.  It is a summary of our assets and liabilities.  The comment at the end of the report said we did not exceed our budget so there is nothing to report.  Kramer made motion to approve the compilation report from Hunt & Associates, Davidson second.  All ayes, motion passed.

The Kristin Nation boat dock easement was introduced by Leonard.  Kristin Nation purchased the property next to the ramp by the south side of the dam from Pam Hargrafen.  Leonard worked with our attorneys to clean up the easement language between us and the new owner.  The District still has to file for the dock permit because we are the owner of the property where Nation will place her dock.  Agreement has been signed by Nation and notorized and Leonard needs board approval to sign on the District’s behalf.  Motion made by Kramer to approve the easement agreement, Davidson second, all ayes, motion passed.

Davidson explained at the last meeting himself, Gifford and Schneider agreed to conduct a meeting with the Lobbyists to better understand their contract and upcoming issues.  Davidson explained due to scheduling conflicts, himself and Kray met with Gary Grant.  Davidson shared a document that Grant provided detailing what his organization had accomplished and additional or ongoing issues.   Gifford said he had some concern about pursuing money so early again and he spoke with Grant and Larry Murphy and they added ideas for grants that are not in the same classification as the funds we already received from the state.  Gifford said he would like to focus on our return on investment.  Kray confirmed with Grant that grant receipt is based on the merit of the request, not legislative influence and Grant indicated that was the case.  Burger said all the Trustees aren’t aware of all the Lobbyists do for us so if we are to move forward, he would want communication not just to the President but to the entire board on a monthly basis.

Kray said the Trustees have not looked at our long term strategy so it is difficult to say what we would have the Lobbyists work on.  She feels we need to do this first before moving forward.   Burger wants to table this for a month so we all can look at it more.  Leonard said the Lobbyists have helped us build a lot of political capital at state house and feel they are a tool for us to use for success in the future. 

Leonard read the job description for the Recording secretary position detailing roles and responsibilities which include recording of minutes and some financial work.  Leonard stated he feels these are 2 separate responsibilities and the Auditor’s office handles our financials.  Burger said we are trying to hire someone to take minutes but asking that they also have a financial background and we are not talking about replacing the Treasurer.  Burger said he feels it would be prudent to move forward to hire a person with these 2 qualifications.  Burger made motion that we refer the Recording Secretary job description to the Budget/Finance committee so they can produce a recommendation for the type of person that we want to hire. Burger said he will step out of this meeting and have Kray replace him as she is the Clerk,  Schneider second.  Leonard asked Carla Becker to explain her role as it pertains to the District’s finances. Becker said her role is to track all funds and handle them according to Iowa code.  She does the same kind of accounting with Delaware County funds as well as the DNR funds so all entities are treated the same.  By allowing the County to handle our accounting, it solved any problems and question of transparency and openness.  In addition, since we were granted state funds, it is now a contractual issue with the state that the County perform our accounting.  Burger restated his motion to refer the job description to the Budget/Finance committee and have them bring their recommendation to the board, Davidson second, all ayes, motion passed.

Colgan discussed the revised operations plan and advised it is not a lot different than the original.  We need to submit this plan to the DNR to show we are capable of operating the dam once it is completed. This is required prior to the DNR providing our permit to impound water.  Our original plan was given to the DNR and the revised plan answers and clarifies their questions about such items as dissolved oxygen levels, freezing conditions, etc.  Most lake properties will see normal lake levels and that is what the operations plan tries to accomplish.  Colgan recommends that the board approve the updated operations plan and if done this evening, the new plan will be submitted tomorrow.  Once this version is forwarded to the DNR, we will see if they have additional questions.  When the DNR approves the revised plan, we should receive the permit about 2 weeks after that.  Motion by Schneider to approve the revised operations plan, Davidson second,  all ayes, motion passed.

Colgan advised we received Change Order #1 from Lunda Construction because of some additional cement that needed to be removed that was not on the original drawings but was found after excavation.  The cement fixture is right where the rock anchors need to go so it is necessary to have it removed.  The amount of the change order is $8,214.50. Motion to approve change order #1 by Gifford, second by Kramer.  All ayes, motion passed.

Burger read Resolution 5.21.14 that allows for change orders in emergency situations.  Motion to approve resolution by Schneider, second by Gifford.  Individual roll call requested, all ayes, motion passed.

Committee updates

Finance – nothing to report

Dam Construction/Timeline – Colgan indicated that river flow has not been a problem for the last 3 weeks.  The rain has restricted work somewhat but the contractor is catching up.  The upstream coffer dam is being worked on.  The most significant news is that the 2 large tubes built in 1928 and used during that construction are not full of concrete and we will hopefully be able to use them, however we need to see both sides of the tubes before that can be determined.  If we can use them, it will reduce the Phase II coffer dam costs. Demolition activity is going on at the top of the dam and they are also pulling out the  old gates in pieces.  Things are going very well.

State/county legislation – Grant said the sales and property tax clarification law went to the Governor’s office on May 9th and it is not signed yet.  He has 30 days to sign but does not see any issues as this is an appropriations bill.

Property Management – Kray asked if the issue with the power in the old house had been resolved so we can get water to the office building.  We have electricity in the office building and there is no electric service at the house where the well is located.  Dave Larson said we need to hire an electrician to see how to get power to the pump.

Leonard thanked Carla Becker for coming today and thanked her for the level of service she gives the District.  He also recognized Shirley Helmrichs, Delaware County Supervisor who was in attendance. Supervisor Helmrichs applauded us as we have come a long way and she doesn’t want to see us go backwards.

Public Comment – Sara Millhouse advised we may want to look at the change order resolution to make sure we don’t have an issue with the open meetings law.  If emails are utilized, it is considered an electronic meeting.  She suggested calling a special meeting or refer the request to a committee.  Burger suggested we have our attorney look at it. 

Motion to adjourn by Davidson, second by Gifford, all ayes, motion passed. Meeting adjourned at 8:13 pm.

Agenda for Trustee Regular Meeting – Wednesday, May 21, 2014

The Combined Lake Delhi Recreational Facility and Water Quality District

Wednesday, May 21, 2014

6:30 p.m.

Heritage Bank Conference Room

Delhi, IA

  1. Call to Order
  2. Approve Agenda
  3. Open Public Hearing for Rocky Nook Area On-Site Wastewater Treatment and Water Main Improvements
  4. Close Public Hearing
  5. Consideration and approval of minutes of Previous Meetings
  6. Consideration and approval of Payments
  7. Review Financial Report
  8. Consideration and approval of annual compilation report by Hunt and Associates
  9. Consideration and possible action on Nation Boat Dock Easement
  10. Consideration and possible action on continuation of Lobbyist contract
  11. Consideration and possible action on Recording Secretary hire
  12. Consideration and possible action on revised Operations Plan
  13. Consideration and possible action on Change Order #1 with Lunda Construction
  14. Consideration and possible action on Change Order Resolution
  15. Committee Updates – Finance, Dam Construction/Timeline, State-County Legislative, Property Management
  16. Public Comment
  17. Adjourn

 

 

Lake Election Time Table

Please find the time table for the upcoming Lake Delhi Trustee election on July 22, 2014.  There are 3 positions available for  3 year terms.

By Monday, May 12, 2014 there will be a copy of the published public notice and a fillable Affidavit of Candidacy form available on the county’s website located at: www.co.delaware.ia.us

 

TIME TABLE

LAKE ELECTION

Tuesday, July 22, 2014

12:00 Noon – 8:00 PM

05/14/2014           Publish Notice of Candidate Filing Deadline

06/06/2014           Last day for Candidates to file Affidavits of Candidacy with Auditor

07/02/2014           Submit Public Notice and Sample Ballot to the Manchester Press

07/07/2014           Worry Free Postmark date

07/09/2014           Public Notice Published in the Manchester Press

07/11/2014           Pre-election Voter Registration Deadline

                                (To have name in election register)

07/12/2014           Auditor’s Office Open on Saturday from 10 am – 2 pm for absentee voting

07/18/2014           Last day to request absentee by mail (5:00pm)

07/22/2014           Absentee Voting open until 11:00 am at Auditor’s Office

                                 Election Day (Polls open from Noon until 8:00 pm)

 

Minutes for Trustee Special Meeting – May 1, 2014

The Combined Lake Delhi Recreational Facility and Water Quality District

Board of Trustees Meeting

Thursday, May 1, 2014 – 2:00 p.m.

Heritage Bank Conference Room

Delhi, IA

The meeting of the Combined Lake Delhi Recreational Facility and Water Quality District Board of Trustees was called to order by President Steve Leonard at 2:04 PM at the Heritage Bank Conference Room.

Trustees present: Leonard,  Kramer, Schneider, Burger, Kray, Gifford by phone

Trustees absent:  Davidson

Visitors: Jim Locke,  Dave Larson, Larry Peter, Pat Dede, Bill Lux, Marcheta Cooey Lux, Pat Anderson,  Gordon Anderson, Tom Cook, Marilyn Cook, Jason Wenger, Sara Millhouse (Dyersville Commercial)

Agenda reviewed by Leonard   He requested to add a timely change for approval of the President signing the document for terrorism insurance included in our business risk insurance.  Motion made by Schneider to approve agenda with timely addition, Kramer second, all ayes, motion passed.  

Leonard advised we added terrorism insurance in our builders risk insurance. The document he needs to sign is simply to say we have this added insurance.  Kramer made motion to approve Leonard to sign the form as we approved the policy at the last meeting, Schneider second.  All ayes, motion passed.

Leonard introduced the document he needed to sign as President that allows for temporary electric service to be installed for the benefit of Lunda Construction.  The district, as the owner of the dam, needs to sign the form allowing the electric service, however, Lunda Construction will be paying for it.  Kramer made motion to approve Leonard to sign the form, Kray second, all ayes, motion passed.

Burger arrived at 2:09 p.m.

Kramer advised the debt service interest only payment for the LDRA for $36,625.00 was due June 1st .  The payment is made to the LDRA to allow them to make their payment to Bank Iowa.  Kramer made motion to approve, Burger second, all ayes, motion passed.

Kramer presented the payment of $674.52 for Pat Colgan’s travel expense (flight and rental car) on his 2/16/2014 trip. Schneider made motion to approve, Kramer second, all ayes, motion passed.

Kramer discussed the need for grounds keeping at the building site by the dam.  The LDRA paid her husband, Randy Kramer last year as grounds keeper.  Her question is if we want him to continue as grounds keeper this year.  His charge is $75/time for mowing.  Motion to approve Randy Kramer to mow the dam building property on an as needed basis at his discretion for $75/event by Burger, Schneider second.  Kramer abstained from voting, remainder all ayes, motion passed.

The Safety and Operations Plan was discussed by Colgan and Holman. Holman indicated this document is required to allow for a permit to impound water.   It describes operating procedures and monitoring and inspection of the dam and is a living document.  As we move forward through Phase I and work into Phase II there will be tweaks to this plan but fundamentally it won’t change.  Colgan said that we can’t finish the operational plan until we receive the gates as we will need more detail.  This document now gives the DNR an opportunity to review it.  Colgan recommends the draft document as written.  Motion to approve Lake Delhi Dam Draft Operation Plan dated May 1, 2014 by Kray, Burger second.   Colgan said 95% of the time there  is nothing to do, it will operate like a fire department for example. Basically, the dam and gates will operate based on the options we pick.  We will need to depend on people to move the gates and that is the seriousness of the plan but in typical summer life, there won’t be much to do but monitor the dam.  Leonard requested a vote on the motion, all ayes, motion passed.

Holman explained the Phase II designs were forwarded to us as they need to be sent to the DNR for permit issuance.  These are essentially the drawings that are ready to go out for bid.  Stanley Engineering will keep the DNR abreast of any changes that will be made, if any, prior to going out to bid.  Motion to approve Lake Delhi Dam Phase II designs by Kramer, Burger second,  all ayes, motion passed.

Jason Wenger from Burrington Group spoke regarding the Rocky Nook Waste Water Treatment and Water Main Project.  Because of the proximity to the river, a traditional system cannot be used so the design is 3 different systems that will connect to up to 7 or 8 cabins each to provide sewage service.  Wenger said he would like to advertise the contracts and solicit bids and then hold a public hearing after the bids are received.  Burger believes according to Iowa code that we have to hold a public hearing first and then notify the bidders. Wenger said they have done it both ways.  It was agreed to set the public hearing for May 21st.    The Bid letting date will be June 10th   at the Delaware County Courthouse at 2PM and then we will award the bids at our regularly scheduled meeting on June 19th.  Designs and drawings will be distributed to the Trustees prior to the May 21st meeting.  Motion authorizing Burrington Group to set the public notice for the bids on May 21st at 6:30 at the Maquoketa Valley Middle School for the public hearing for the Rocky Nook Water Waste Water Treatment and Water Main Project by Burger, Schneider second, all ayes, motion passed.

Public Comments was added to the meeting and Larry Peter asked if the state tax issue was approved last night.  Leonard advised yes.  Peter also asked what was the feedback like from the DNR letter.  Leonard said there were a few responses that voice concern but the DNR will be responding to them shortly.  Peter than asked if the DNR has to sign off on change orders.  Colgan advised no, only if we were changing something fundamentally.

Motion to adjourn meeting by Burger, Kramer second, all ayes, motion passed.   Meeting adjourned at 2:48 pm.

Agenda for Trustee Special Meeting – May 1, 2014

The Combined Lake Delhi Recreational Facility and Water Quality District

Thursday, May 1, 2014

2:00 p.m.

Heritage Bank Conference Room

Delhi, IA

  1. Call to Order
  2. Approve Agenda
  3. Approval of President to sign Alliant Commercial Service Application
  4. Consideration and possible action on payment of interest only LDRA Debt Service
  5. Consideration and possible action on payment of Colgan travel expense
  6. Consideration and possible action on grounds keeping in the dam site area
  7. Consideration and possible action of Safety and Operations Plan
  8. Consideration and possible action of Phase II designs

  9. Consideration and possible action of authorizing Burrington Group, Inc. to publish “Notice to Bidders and Notice of Public Hearing” for the Rocky Nook area on-site Waste Water Treatment and Water Main project

  10. Adjourn

 

 

Immediately Following – WORK SESSION

 

  • Work Session – Lake Delhi Combined Recreational Facility and Water Quality District Board of Trustees
    • Draft change order policy, communication and procedures
    • Draft recording secretary job description